Northern Beaches water network upgrade
As part of a $31M strategy to improve supply and reliability of water to the northern beaches, Council is undertaking works over a 10-year program which includes installing and replacing water pipes within the Cairns water supply network to allow increased water flow and reduce breakages. Once complete, the northern beaches community from Palm Cove to Yorkeys Knob and Lake Placid (approx. 34,000 residents) will benefit from the upgraded infrastructure and should experience less water interruptions.
Timeframe
Works are programmed over eight stages, with stage six underway in Kamerunga, and is expected to be completed by June 2021 subject to favourable weather conditions. Residents and businesses in the area will be continually updated throughout the life of the project. The community are encouraged to visit the Works In Progress page for project updates.
- Stage 1 - $5.8 M Palm Cove and Clifton Beaches Trunk Water Mains – completed 2015
- Stage 2 – $ 4.6 M Caravonica Trunk Water Main – completed 2017
- Stage 3 – $ 4.3 M Brinsmead Terrace Water Main – completed 2018
- Stage 4 – $ 1.2 M Trinity Beach and Thomatis Creek Water Main Replacements – completed 2019
- Stage 5 – $ 2.5 M Dunne Road Smithfield – completed 2020
- Stage 6 – $6.0 M Kamerunga Road Water Main – currently underway
- Stage 7 - $3.3 M Trinity Beach Water Mains and Booster Pump Station – planned for completion by December 2026
- Stage 8 - $3.3 M Paradise Palms to Clifton Beach Trunk Water Main – planned for completion by June 2032
Project enquiries can be emailed to wwfeedback@cairns.qld.gov.au
Last Updated: 7 October 2025
Latest News > All News
Free green waste disposal and sandbags
With the wet season upon us, residents are encouraged to clear excess vegetation from their properties using Council’s free green...
10 November 2026
Have your say on future dog off-leash areas
Are you a regular user of any of Cairns’ designated dog off-leash areas? Cairns Regional Council is seeking community feedback...
10 November 2026
New Cairns airport bus cleared for takeoff
Travelling from Cairns airport into the CBD will now be a streamlined experience with the new Route 100 service taking...
3 November 2026