The Planning Act 2016 defines Operational work as 'work, other than building work or plumbing or drainage work, in, on, over or under premises that materially affects premises or the use of premises'. The works may be on public or private land.

Examples of operational works include:

  • Driveways and crossovers
  • Road works, including an existing road or new roads
  • Clearing vegetation (damage to vegetation)
  • Stormwater works, above and below ground
  • Water infrastructure (excluding plumbing and drainage work)
  • drainage work
  • excavating or filling of land (except where Building Work under a Building Permit)
  • Sewerage infrastructure (excluding plumbing and drainage work)
  • trimming (pruning) and damaging (clearing) vegetation
  • landscaping works (typically associated with other Development Permits (MCU, ROL)
  • undertaking tidal works (prescribed tidal works)
  • Electrical and streetlighting works (typically associated with other Development Permits)

The CairnsPlan 2016 Planning Scheme sets out when Operational Work requires a Development Permit and the requirements to address for Applications. Operational work is a type of Development Permit. Therefore it must be assessed in accordance with legislative time frames prescribed under Development Assessment Rules within the Planning Act 2016.

Post-approval process

Our step-by-step guidelines and application forms will help you navigate each step for a quicker turnaround time. These forms include any FNQROC forms as required, all in one place. The guidelines are a step-by-step guide to completing the form as well as an excellent source of information about the element of Post Approval you may be applying for.

All applications will be processed in a two-step approach - initial assessment and technical assessment. This will allow greater transparency and consistency for everyone involved. The two-step process allows our technical officers and inspectors to complete more “on the ground” tasks, faster. This will result in more efficient approvals and certifications across the region.

By submitting a complete and compliant application, you will ensure a quicker turnaround time for your approval and your project.

Operational Works Pre-Start

After Operational Works Approval or Planning Approval has been received and prior to construction works beginning, there are several criteria and steps to be completed.

Landscape Plan Endorsement

Information on how to receive a Landscape Plan Endorsement where required under a condition of a Development Approval.

Works Acceptance

A Works Acceptance is required after construction works have been completed, where Council will be accepting ownership of certain assets at the site, for example drains, roads, sewerage and water infrastructure or greenspaces.

Early Plan Sealing

Early Plan Sealing is an option for some developments to enable an early approval of the Plan of Subdivision, prior to full completion of works required for the development, at Council’s discretion.

Landscaping Practical Completion

Information on how to pass a Landscaping Practical Completion Inspection and receive a Landscaping Practical Completion Endorsement.

Final Works Acceptance

Final Works Acceptance Certification is the concluding step in the Post Approval process.

Bonds

Council charges security bonds (payable in cash, cheque or bank guarantee only) for Operational works:

As Constructed Data Certification

Council has adopted the As Constructed Design Certification (ACDC) online solution for the submission of as-constructed information.

Express DA

Express DA is an accelerated assessment initiative offering a simple, faster way to progress low-risk development applications. Development industry representatives can participate by attaining Express DA accreditation.

Vegetation clearing

Trees and vegetation form an integral part of our urban forest. If a property owner wishes to remove or damage any vegetation on their property, a Development Permit for Operational Works (Vegetation Clearing) may be required.

Last Updated: 24 July 2025

Latest News > All News

New chapter for Cominos House community hub

Cominos House in Manunda will continue to serve the community as a valued local facility, with Council approving a new...

Community & Lifestyle
25 June 2026

Waste fee changes to support fair services

Cairns Regional Council is updating fees and charges at its transfer stations from 1 July to ensure waste services remain...

General Updates
25 June 2026

New strategy for a more resilient Cairns

Today, Council endorsed the Cairns Social Resilience Strategy 2026–2030, establishing a framework to strengthen social resilience across the region and...

Community & Lifestyle
24 June 2026