Redlynch Village intersection upgrade

  • Type of work: Major Infrastructure Project
  • Suburb: Redlynch
  • Work period (anticipated): 12/08/2019 to 31/03/2020
  • Description: Major intersection upgrade
  • Likely impacts: Noise; Dust; Property Access; Traffic Control
  • Location: Kamerunga Rd / Redlynch Intake Rd intersection
  • Status: Open
Project update

This project is approximately 77% complete.  Works near the Red Beret Hotel and Dunham Realty are nearing completion.

Works are underway near the Redlynch Village shopping centre / IGA corner and the rail line side of Kamerunga Rd. Some car parks will have to be closed while this work is in progress - please note that additional car parking is available north of the rail line on Kamerunga Rd.

The bus stop opposite the Red Beret Hotel has been moved further east down Kamerunga Rd.

All project works are estimated to be complete by March 2020, weather permitting, and we thank you for your continued patience during this project.

The Kamerunga Road / Redlynch Intake Road intersection will undergo a major transformation this year.

This project aims to address road safety concerns for motorists, pedestrians and cyclists by providing an improved streetscape and village atmosphere within a low-speed environment.

Works will be staged to ensure pedestrian and vehicular access to the village zone can be maintained throughout construction.

Construction works are programmed to start from Monday 19 August 2019 and are estimated to be complete by February 2020, weather permitting. Preparation works will be underway from Tuesday 13 August 2019.

Temporary lane closures will be required and traffic delays are expected.

Noise and dust is also expected and car parking bays near the work sites will have to be temporarily closed at times. There will also be temporary disruptions to driveways at times.

The bus stop on the northern side of Kamerunga Rd will also have to be temporarily relocated approximately 70m eastwards.

Every effort will be made to reduce disruptions during this time.

Thank you for your patience during construction. For further information, please visit the Major Projects webpage .