Footpath Works - White Rock

  • Type of work: Footpath & Cycleway Works
  • Suburb: White Rock
  • Work period (anticipated): 05/05/2020 to 31/12/2020
  • Description: Footpath upgrade works
  • Likely impacts: Noise; Dust; Property Access
  • Location: Various locations
  • Status: Open
Project Update

The White Rock Connectivity Program is nearing completion with construction commencing on the remaining sections of pathway during the week of Monday 17 August 2020.

Works will include:

  • Footpath construction across Sheehy Rd to complete this link; and
  • Construction of the pedestrian crossing over Sawpit Gully between Hopkins St and Colombia St

Project completion is estimated for September 2020.

Council appreciates your patience and cooperation during this time.

The following footpath upgrade works are programmed for White Rock from TUESDAY 5 MAY 2020 (weather permitting).

Type of Works:

  • Footpath construction - northern side of Phoenix St from Tiffany St intersection and tying in with the existing path east of 21 Phoenix St - completed
  • Pram ramp construction near Goldberg Close - completed
  • Footpath construction - eastern side of the drain from Leftwich St to Phoenix St - completed
  • Drain crossing construction between Hoffman Close and Sheehy Road - completed
  • Footpath construction - unoccupied side of Tarantino Crescent and in the greenspace corridor behind Colombia St and Disney St

These links form part of the White Rock footpath linkages project which will provide a ~2.5km walking track loop.

Please observe and obey traffic controllers and signs advising the changes to normal traffic conditions.

Council appreciates your patience and cooperation during this time.

Last updated: 31 July 2020