Northern Beaches Leisure Trail - Clifton Beach North

  • Type of work: Footpath & Cycleway Works
  • Suburb: Clifton Beach
  • Work period (anticipated): 07/01/2019 to 30/06/2019
  • Description: A new pathway will be constructed along the northern foreshore of Clifton Beach.
  • Likely impacts: Noise; Dust
  • Location: Upolo Esplanade foreshore, Yule Ave to Delaney's Ck
  • Status: Open
Project update

Construction is underway on the elevated walkway at Delaney's Creek. The rest of this project is currently on hold while alignment options are further explored.

Pathway works for the Clifton Beach foreshore are expected to commence on 7 January 2019, weather permitting.

The pathway will extend from Yule Ave in the south through to Delaney’s Creek in the north.

It will include:

  • construction of a 3-metre wide shared pathway, finished with exposed aggregate concrete, running adjacent to Upolo Esplanade from Yule Ave in the south through to Delaney’s Creek in the north;
  • construction of an elevated walkway at Delaney’s Creek to connect to the existing Argentea pathway; and
  • installation of an elevated walkway adjacent to Deadman’s Gully, just north of Endeavour Rd.

Several trees will need to be removed to complete this project, however, tree removals will be minimised wherever possible.

Works are expected to be complete by June 2019, weather permitting. 

Should you require further information or would like to provide feedback, please call 4044 3303 or email feedback@cairns.qld.gov.au.

Last updated: 11 February 2019