Chinaman Ck drain works

  • Type of work: Drainage Works
  • Suburb: Mooroobool
  • Work period (anticipated): 07/08/2019 to 13/09/2019
  • Description: Repairs to concrete lined drain
  • Likely impacts: Noise; Dust; Property Access
  • Location: Near Frances St
  • Status: Open

Drainage improvement works are programmed for the Chinaman Creek Drain, Mooroobool.

This work will involve removing and replacing damaged sections of the concrete lined drain that runs along the rear of properties at no. 26 Lois Street, from no.1 to no. 7 Francis Street and the First City Caravilla caravan park.

Works are programmed to start the week of Wednesday 7 August 2019.

It is expected to take approximately 5 weeks to complete the project, weather permitting.

During construction, there may be noise associated with the works, as well as machinery and trucks entering and leaving the site however, Council officers will minimise temporary inconveniences wherever possible.

Council appreciates your patience during these improvement works. For further information, please email feedback@cairns.qld.gov.au.