Roadworks - Golden Grove Dve & Currawong St

  • Type of work: Minor Road Works
  • Suburb: Bentley Park & Bayview Heights
  • Work period (anticipated): 08/05/2018 to 31/05/2018
  • Description: Traffic management device improvements.
  • Likely impacts: Noise; Dust; Traffic Control
  • Location: Golden Grove Drive & Currawong Street
  • Status: Closed

Roadworks are programmed to start in Golden Grove Drive and Currawong Street on Tuesday 8 May.

This work involves replacing existing rubber speed humps with concrete.

Expect minor delays during this time.

All works are expected to be complete by the end of May 2018. Please note that ten (10) days are needed for concrete curing before they can be trafficable.