Roadworks - Jones St

  • Type of work: Minor Road Works
  • Suburb: Westcourt
  • Work period (anticipated): 28/10/2019 to 04/11/2019
  • Description: Kerb and channel replacement between Mann St and Gatton St
  • Likely impacts: Noise; Dust; Property Access; Traffic Control
  • Location: Jones St
  • Status: Closed

The following improvement works are programmed for Jones St from MONDAY 28 OCTOBER 2019, weather permitting.

Type of work:  Kerb and channel and associated road repairs to some sections of the eastern side of Jones St (between Mann St and Gatton St).

Duration:  Approx.1 week to complete, weather permitting from 7am – 5pm

Please observe and obey traffic controllers and signs advising the changes to normal traffic conditions.

Council appreciates your patience and cooperation during this time.

For further information, please email feedback@cairns.qld.gov.au

Last updated: 04 November 2019