Roadworks - Hutchinson St

  • Type of work: Drainage Works
  • Suburb: Edge Hill
  • Work period (anticipated): 08/09/2020 to 14/09/2020
  • Description: Stormwater drain replacement
  • Likely impacts: Noise; Dust; Traffic Control; Road Closure
  • Location: Hutchinson St
  • Status: Closed

The following drainage improvement works are programmed for HUTCHINSON STREET:

  • Type of work: Removal and replacement of the stormwater pipe that runs underneath Hutchinson St, west of the Junction Street intersection
  • Dates: From TUESDAY 8 SEPTEMBER 2020
  • Approx. duration: Approx. 1 week to complete (weather permitting)
  • Working hours: Monday to Friday 7am – 5pm, Saturday 7am – 1pm if required

During construction, a temporary road closure will be required.

There may also be temporary disruptions such as noise and dust however, Council will minimise inconveniences wherever possible.

Please observe and obey traffic controllers and signs advising the changes to normal traffic conditions, and follow detours as sign posted.

Council appreciates your patience and cooperation during this time.