Holloways Beach Foreshore Improvement

Project Update

Approximately 80% of this project is now complete. Works remaining include:

  • completion of the footpath within the southern area and a new traffic speed hump;
  • a new playground;
  • electrical, irrigation, street lighting and CCTV works;
  • furniture installation including new shelters and BBQs; and
  • bollard installation.

A $3 million makeover of the Holloways Beach foreshore will include new barbecues, shelters and playground equipment.

Parking will be improved on Casuarina Street and the intersection with Luke Street will be re-opened to create a new one-way northbound access.

Other improvements will include new lighting, CCTV cameras, irrigation systems, rubbish bins, seating, bubblers, landscaping and a pedestrian crossing for safe access across Oleander Street.

The project is partially funded through the Queensland Government’s Works for Queensland program and is expected to be completed by June 2019.

Other Council works in the immediate area will be programmed to occur concurrently, including pavement rehabilitation works, kerb and channel replacement and the Machans Beach – Holloways Beach section of the Northern Beaches Leisure Trail.

Key dates

Council endorsed the Holloways Beach Foreshore Improvement Plan ( PDF, 1.82 MB ) at the Sport and Community Services meeting held 21 June 2017.

On 26 September 2018, Council approved the Project Launch Approval ( PDF, 0.59 MB ) for the project, to progress the key upgrade improvement works.

Plan showing works to Casuarina Street and Oleander Street, Holloways Beach Foreshore. Works include new raised pedestrian crossing with associated lighting, reconfigured carparking, new playground, new leisure trail and one-way configuration of Casuarina Street.